1
单选题
1分
Checklists are completed in which process?
A.
) Risk identification.
B.
) Quality assuranc
C.
) Quality planning.
D.
) Quality control.
点击查看答案
2
单选题
1分
An early version of one of W. Edward Deming's 14 points encouraged companies to “cease dependence on mass inspection by building quality into the product in the first place”. Deming stated that, typically, products are inspected as they come off the line or at major stages. Defective products are either thrown out or reworked. Both options are expensive. This approach, in effect, meant that companies would pay workers to make defects and then correct them. Denting later recognized the value of inspections and revised the point to say that people should “understand the purpose of inspection. ” He said, “Inspections must be carried out in a professional way, not by lick-spit methods. ” This supports the PMBOK, which indicates that inspections can be used to determine whether results conform to requirements. Inspections also may be called ______ .
A.
) control tests
B.
) walk-through
C.
) statistical sampling
D.
) checklists
点击查看答案
3
单选题
1分
Investment in product quality improvement, especially defect prevention and appraisal, can often be borne by ______ .
A.
) the organization
B.
) the project management team
C.
) executive management
D.
) the project
点击查看答案
4
单选题
1分
A project team is in the design stage of a new mountain bike prototype. The team is in the process of identifying which type of frame and material will provide high performance at a low cost. Which of the following is the MOST likely technique used to determine these variables?
A.
) Benefit/cost analysis.
B.
) Ishikawa diagram.
C.
) Design of experiments.
D.
) System flow chart.
点击查看答案
5
单选题
1分
A team member notices the project manager that a quality measurement for the project can not be met. What should the project manager do?
A.
) Notify management.
B.
) Hold a team meeting.
C.
) Look for alternative ways to meet the quality level.
D.
) Ask management tp come up with options.
点击查看答案
百度扫一扫练题
关注千题库公众号
PMP资格认证考试-题库
千题库下载
历年真题
历年考试真题试卷, 真实检验
章节练习
按章节做题, 系统练习不遗漏
考前押题
考前押题, 提高分数
模拟试题
海量考试试卷及答案, 分数评估
进入题库
相关试卷
综合练习
章节练习
组织影响与项目生命周期
项目整合管理(四)
项目整体管理
项目质量管理
项目质量管理(一)
项目质量管理(二)
项目质量管理(三)
项目质量管理(四)
项目质量管理(五)
引论
收藏本站
Ctrl+D
将本站加入到书签,做题找题搜题,快速快捷。
下载App
微信扫一扫打开
回到顶部