1
单选题
1分
There are specific absolutes for a comprehensive quality program. These are ______.
A.
conformance to WBS
B.
fitness of use and involvement during the planning phase
C.
fitness of use and fitness for purpose
D.
none of the above
点击查看答案
2
单选题
1分
A Pareto diagram is used to ______.
A.
identify nonconformity types
B.
provide a quick look at the data at a single point in time
C.
determine the effect of a corrective action
D.
determine the equation of a scatter plot
点击查看答案
3
单选题
1分
Product availability contains ______.
A.
usability and maintainability
B.
producibility and maintainability
C.
usability and reliability
D.
reliability and maintainability
点击查看答案
4
单选题
1分
The process control charts are used ______.
A.
to graph what typically focuses on the prevention of a problem
B.
to detect the problem
C.
to reject the problem
D.
to determine the acceptability of the sample
点击查看答案
5
单选题
1分
Setting the number of defects is a direct responsibility of ______.
A.
a functional worker
B.
the project manager
C.
management
D.
the accounting department
点击查看答案
百度扫一扫练题
关注千题库公众号
PMP资格认证考试-题库
千题库下载
历年真题
历年考试真题试卷, 真实检验
章节练习
按章节做题, 系统练习不遗漏
考前押题
考前押题, 提高分数
模拟试题
海量考试试卷及答案, 分数评估
进入题库
相关试卷
综合练习
章节练习
组织影响与项目生命周期
项目整合管理(四)
项目整体管理
项目质量管理
项目质量管理(一)
项目质量管理(二)
项目质量管理(三)
项目质量管理(四)
项目质量管理(五)
引论
收藏本站
Ctrl+D
将本站加入到书签,做题找题搜题,快速快捷。
下载App
微信扫一扫打开
回到顶部