单选题 1分

Crashing in time management is ______ .

  • A.a schedule compression technique that typically includes reducing schedule activity durations and increasing the assignment of resources to schedule activities
  • B.a schedule compression technique in which phases or activities that normally would be done in sequence are performed in parallel
  • C.the timely input of data to calculate the critical path
  • D.equivalent to minimizing float

你可能感兴趣的试题

1 单选题 1分
  • A.Fast track the project to ensure that the project schedule is not delaye
  • B.Review the performance reports to determine which planned dates have not been met, and the impact on critical pat
  • C.Try to get additional supplies from an alternate location as soon as possibl
  • D.Take corrective action to minimize the impact because of the dela
3 单选题 1分
  • A.the critical path is reduced
  • B.the contingency is no longer available
  • C.no float time is available
  • D.project resources are reduced
4 单选题 1分
  • A.Start-to-start, start-to-finish, finish-to-finish, finish-to-star
  • B.Early start, early finish, late start, late finis
  • C.Predecessor-to-successor, predecessor-to-predecessor, successor-to-successo
  • D.Primary-to-secondary, primary-to-finish, secondary-to-secondary, finish-to-finis