单选题 1分

At the end of the closing process group, ______.

  • A.) it is verified that the defined processes are completed within all the process groups to close the project phase
  • B.) it is determined that the product of the project is completed satisfactorily
  • C.) project management plan is written off by the project sponsor
  • D.) new change requests are initiated as required