单选题 1分

If a CV was positive and the SV was positive, what does this indicate?

  • A.) The project is over budget, but on schedules.
  • B.) The project is under budget, but behind schedules.
  • C.) The project is under budget, and ahead of schedules.
  • D.) The project is on budget and on schedules.