单选题 1分

In your project, some requested changes were generated from the activity definition process. These c...

In your project, some requested changes were generated from the activity definition process. These changes will be processed through ______ .
  • A.activity change control system
  • B.corrective action
  • C.integrated change control system
  • D.activity sequencing

你可能感兴趣的试题

1 单选题 1分
  • A.Fast track the project to ensure that the project schedule is not delaye
  • B.Review the performance reports to determine which planned dates have not been met, and the impact on critical pat
  • C.Try to get additional supplies from an alternate location as soon as possibl
  • D.Take corrective action to minimize the impact because of the dela
3 单选题 1分
  • A.the critical path is reduced
  • B.the contingency is no longer available
  • C.no float time is available
  • D.project resources are reduced
4 单选题 1分
  • A.Start-to-start, start-to-finish, finish-to-finish, finish-to-star
  • B.Early start, early finish, late start, late finis
  • C.Predecessor-to-successor, predecessor-to-predecessor, successor-to-successo
  • D.Primary-to-secondary, primary-to-finish, secondary-to-secondary, finish-to-finis