单选题 1分

You are the project manager of Alpha Network Inc.Your company is doing network planning for a major ...

You are the project manager of Alpha Network Inc.Your company is doing network planning for a major bank.You are planning to digram the activity dependancies using activity list.Which of the following is true?
  • A.PDM is also the AOA diagramming metho
  • B.PDM is also the AOD digramming metho
  • C.PDM is also AON digramming metho
  • D.PDM is also ADM diagramming metho