Since you are in the preliminary stages of your project, you estimate that your project will most probably last 1 year-however, optimistic scenario is that it will get over within 6 months and pessimistic scenario is 18 months. This kind of estimate is also called ______ .
  • A.) definitive
  • B.) capital cost
  • C.) order of magnitude
  • D.) feasibility