单选题 1分

Resource calendars affect a specific resource or category of resources. They reflect how some resour...

Resource calendars affect a specific resource or category of resources. They reflect how some resources work only during normal business hours, while others work three full shifts, or a project team member might be unavailable, such as on vacation or in a training program, or a labor contract can limit certain workers to certain days of the week. Resource calendars are valuable inputs for ______ .
  • A.developing an approximation of the costs of the resources needed to complete each schedule activity
  • B.aggregating the estimated costs of individual schedule activities or work packages to establish a total cost baseline for project performance
  • C.searching the cause of positive and negative variances as part of integrated change control process
  • D.assuring that potential cost overruns do not exceed the authorized funding periodically and in total for the project

你可能感兴趣的试题

1 单选题 1分
  • A.Fast track the project to ensure that the project schedule is not delaye
  • B.Review the performance reports to determine which planned dates have not been met, and the impact on critical pat
  • C.Try to get additional supplies from an alternate location as soon as possibl
  • D.Take corrective action to minimize the impact because of the dela
3 单选题 1分
  • A.the critical path is reduced
  • B.the contingency is no longer available
  • C.no float time is available
  • D.project resources are reduced
4 单选题 1分
  • A.Start-to-start, start-to-finish, finish-to-finish, finish-to-star
  • B.Early start, early finish, late start, late finis
  • C.Predecessor-to-successor, predecessor-to-predecessor, successor-to-successo
  • D.Primary-to-secondary, primary-to-finish, secondary-to-secondary, finish-to-finis