单选题 1分

Your project is in the planning phase and you are paid every fortnight for the work to be done durin...

Your project is in the planning phase and you are paid every fortnight for the work to be done during the fortnight. You have been informed by the project sponsor that there has been a revaluation of projects within your company and your project will not be getting any additional funding. In this case, you should ______.
  • A.stop work immediately and release all resources
  • B.perform appropriate closure for the project
  • C.decrease team size
  • D.remove non-critical tasks to decrease cost