单选题 1分

The relationship between project management process groups and project life cycle phases is best des...

The relationship between project management process groups and project life cycle phases is best described by the following:
  • A.They are unrelated, incompatible concept
  • B.They are the same concept described by different terms to satisfy application area extension
  • C.Phases cross process groups such that closing one process group provides an input to initiating the next phas
  • D.Process groups interact within a project phase and also may cross the project phase

你可能感兴趣的试题

1 单选题 1分
  • A.portfolio management
  • B.management by projects
  • C.management by objectives
  • D.management by exception
3 单选题 1分
  • A.is wasteful and should be avoided whenever possible
  • B.helps to keep the project focused on the business need that the project was undertaken to address
  • C.helps ensure that the project continues regardless of changes in the business needs
  • D.helps ensure continuous employment of project team members even if the project is unlikely to satisfy the business need that it was undertaken to address
4 单选题 1分
  • A.functional
  • B.weak matrix
  • C.projectized
  • D.small capitalization
5 单选题 1分
  • A.develop project charter
  • B.create WBS
  • C.estimate costs
  • D.sequence activities