1
单选题
1分
Of the following estimates, which most accurately reflect the actual cost of the project?
A.
) Conceptual estimates.
B.
) Order of magnitude estimates.
C.
) Preliminary estimates.
D.
) Bottom-up estimat
点击查看答案
2
单选题
1分
Your company has established a reward and recognition system for its project management professionals. Project cost performance is used as a criterion to determine rewards. What should you do to ensure that rewards reflect actual performance?
A.
) Consider overtime work as part of the jo
B.
) Prepare a cost baselin
C.
) Use earned value management to monitor performanc
D.
) Estimate and budget controllable and uncontrollable costs separately.
点击查看答案
3
单选题
1分
Given: BAC=200, AC=120, EV=80, CPI=0.666. Assuming that current variances are atypical, and that similar variances will not occur in the future, the estimate at completion (EAC) is ______ .
A.
) 120
B.
) 160
C.
) 200
D.
) 240
点击查看答案
4
单选题
1分
As a project manager, you are aware that estimating schedule activity costs involves developing an approximation of the costs of the resources needed to complete each schedule activity. In approximating costs, the estimator considers the possible causes of variation of the cost estimates, including risks. Cost estimating includes identifying and considering various costing alternatives. For example, in most application areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution and product operations. The cost estimating process considers whether the expected savings can offset the cost of additional design work. Cost estimates are generally expressed in units of currency to facilitate comparisons both within and across projects. Cost estimates can also benefit from refinement during the course of the project to reflect on the additional detail available. For your project, which is in the initial phases, your team suggested a rough order of magnitude estimate—this could be in the range of ______ .
A.
) -75% to+125%
B.
) -50% to+100%
C.
) -25% to+50%
D.
) None of the above
点击查看答案
5
单选题
1分
A project management professional can compare earned value performance data to all of the following project management tools EXCEPT ______ .
A.
) critical path analysis
B.
) technical performance metrics
C.
) risk mitigation plans
D.
) forecasted final costs and schedule estimates
点击查看答案
百度扫一扫练题
关注千题库公众号
PMP资格认证考试-题库
千题库下载
历年真题
历年考试真题试卷, 真实检验
章节练习
按章节做题, 系统练习不遗漏
考前押题
考前押题, 提高分数
模拟试题
海量考试试卷及答案, 分数评估
进入题库
相关试卷
综合练习
章节练习
组织影响与项目生命周期
项目整合管理(四)
项目整体管理
项目质量管理
项目质量管理(一)
项目质量管理(二)
项目质量管理(三)
项目质量管理(四)
项目质量管理(五)
引论
收藏本站
Ctrl+D
将本站加入到书签,做题找题搜题,快速快捷。
下载App
微信扫一扫打开
回到顶部