单选题
1分
You are the project manager of Alpha Network Inc.Your company is doing network planning for a major ...
You are the project manager of Alpha Network Inc.Your company is doing network planning for a major bank.You are planning to digram the activity dependancies using activity list.Which of the following is true?
参考答案: C
参考解析: [解析] 你是Alpha网络公司的项目经理。你们公司在为一个大银行架构网络规划。你计划使用网络图来表现活动列表中活动的依赖关系。下列哪个说法是正确的?
A) PDM又被称为AOA绘图法。 B) PDM又被称为AOD绘图法。
C) PDM又被称为AON绘图法。D) PDM又被称为ADM绘图法。
PDM叫前导图,又被称为“活动在节点上(AON)”;AOA是“活动在箭线上”,是ADM的另一个名字。