单选题 1分

In your project,you can use all the following tools and techniques for risk response planning EXCEPT...

In your project,you can use all the following tools and techniques for risk response planning EXCEPT______.
  • A.strategies for negative risks or threats
  • B.contingent response planning
  • C.strategy for threat and opportunities
  • D.strategy for residual risks