If task A has seven days of free float and 15 days of total float and the early start date is delayed 5 days, what does this do to the completion date of the project?
A.
) Pushes the finish date out ten days.
B.
) Delays the early start date of the next dependent task five days.
C.
) Allows the project to finish five days earlier.
D.
) The finish date doesn't chang
点击查看答案
2
单选题
1分
If Task B has 15 days of free float and 25 days of total float, and the early start date of Task B is delayed 30 days, how is the project affected?
A.
) The next dependent task's start date will be delayed 15 days.
B.
) The duration of the task will be shortened 15 days.
C.
) The completion date of the project will be pushed out 5 days.
D.
) Both A and
点击查看答案
3
单选题
1分
If Task C has 0 days of free float and 0 days of total float, what does this mean to the project?
A.
) The project does not have adequate lead and lag times built in.
B.
) The task is on the critical path.
C.
) The duration of the task should be compresse
D.
) The dates for the task are not accurat
点击查看答案
4
单选题
1分
A master schedule is delayed or an executive presentation. What information must the PM gather to complete this schedule?
A.
) Dates of major activities.
B.
) Key milestones.
C.
) Summary level task descriptions.
D.
. All of abov
点击查看答案
5
单选题
1分
What is one of the key problems with using crashing rather than fast tracking to compress project duration?
A.
) Personnel overlap.
B.
) Budget constraints.
C.
) Sub-dividing critical path tasks to work in parallel.
D.
) Finish to start relationships are modifie
点击查看答案
百度扫一扫练题
关注千题库公众号
PMP资格认证考试-题库
千题库下载
历年真题
历年考试真题试卷, 真实检验
章节练习
按章节做题, 系统练习不遗漏
考前押题
考前押题, 提高分数
模拟试题
海量考试试卷及答案, 分数评估
进入题库
相关试卷
综合练习
章节练习
组织影响与项目生命周期
项目整合管理(四)
项目整体管理
项目质量管理
项目质量管理(一)
项目质量管理(二)
项目质量管理(三)
项目质量管理(四)
项目质量管理(五)
引论
收藏本站
Ctrl+D
将本站加入到书签,做题找题搜题,快速快捷。
下载App
微信扫一扫打开
回到顶部