项目时间管理(二)

题量:20题
题型:单选题
试卷简介: 项目时间管理(二), 此试卷为参加"PMP资格认证考试"的考生提供的"项目时间管理(二)"的答案和解析。

试题预览

1 单选题 1分
  • A.) Pushes the finish date out ten days.
  • B.) Delays the early start date of the next dependent task five days.
  • C.) Allows the project to finish five days earlier.
  • D.) The finish date doesn't chang
2 单选题 1分
  • A.) The next dependent task's start date will be delayed 15 days.
  • B.) The duration of the task will be shortened 15 days.
  • C.) The completion date of the project will be pushed out 5 days.
  • D.) Both A and
3 单选题 1分
  • A.) The project does not have adequate lead and lag times built in.
  • B.) The task is on the critical path.
  • C.) The duration of the task should be compresse
  • D.) The dates for the task are not accurat
4 单选题 1分
  • A.) Dates of major activities.
  • B.) Key milestones.
  • C.) Summary level task descriptions.
  • D.. All of abov
5 单选题 1分
  • A.) Personnel overlap.
  • B.) Budget constraints.
  • C.) Sub-dividing critical path tasks to work in parallel.
  • D.) Finish to start relationships are modifie