What is one of the key problems with using crashing rather than fast tracking to compress project du...

What is one of the key problems with using crashing rather than fast tracking to compress project duration?
  • A.) Personnel overlap.
  • B.) Budget constraints.
  • C.) Sub-dividing critical path tasks to work in parallel.
  • D.) Finish to start relationships are modifie

你可能感兴趣的试题

1 单选题 1分
  • A.) Pushes the finish date out ten days.
  • B.) Delays the early start date of the next dependent task five days.
  • C.) Allows the project to finish five days earlier.
  • D.) The finish date doesn't chang
2 单选题 1分
  • A.) The next dependent task's start date will be delayed 15 days.
  • B.) The duration of the task will be shortened 15 days.
  • C.) The completion date of the project will be pushed out 5 days.
  • D.) Both A and
3 单选题 1分
  • A.) The project does not have adequate lead and lag times built in.
  • B.) The task is on the critical path.
  • C.) The duration of the task should be compresse
  • D.) The dates for the task are not accurat
4 单选题 1分
  • A.) Dates of major activities.
  • B.) Key milestones.
  • C.) Summary level task descriptions.
  • D.. All of abov
5 单选题 1分
  • A.) Personnel overlap.
  • B.) Budget constraints.
  • C.) Sub-dividing critical path tasks to work in parallel.
  • D.) Finish to start relationships are modifie