You got news that because of bad weather, your shipment has got delayed by 2 weeks。What should be the first step that you take?
A.
Fast track the project to ensure that the project schedule is not delaye
B.
Review the performance reports to determine which planned dates have not been met, and the impact on critical pat
C.
Try to get additional supplies from an alternate location as soon as possibl
D.
Take corrective action to minimize the impact because of the dela
点击查看答案
2
单选题
1分
Critical chain is a schedule network analysis technique that modifies the project schedule to account for limited resources. Critical chain combines deterministic and probabilistic approaches. Initially, the project schedule network diagram is build using non-conservative estimates for activity durations within the schedule model, with required dependencies and defined constraints as inputs. The critical path is then calculated. After the critical path is identified, resource availability is entered and the resource-limited schedule result is determined. The resulting schedule often has an altered critical path. The critical chain method adds non-work schedule activities to maintain focus on the planned activity durations, also referred to as ______ .
A.
duration buffers
B.
resource leveling
C.
reverse resource leveling
D.
crashing
点击查看答案
3
单选题
1分
A project schedule completion date will change if ______ .
A.
the critical path is reduced
B.
the contingency is no longer available
C.
no float time is available
D.
project resources are reduced
点击查看答案
4
单选题
1分
The critical path is established by calculating the following dates:
A.
Start-to-start, start-to-finish, finish-to-finish, finish-to-star
B.
Early start, early finish, late start, late finis
C.
Predecessor-to-successor, predecessor-to-predecessor, successor-to-successo
D.
Primary-to-secondary, primary-to-finish, secondary-to-secondary, finish-to-finis
点击查看答案
5
单选题
1分
Activities that are related and shown as a single, aggregate activity reported at a summary level are called ______ .
A.
master schedule
B.
hammock
C.
WBS
D.
hanger
点击查看答案
百度扫一扫练题
关注千题库公众号
PMP资格认证考试-题库
千题库下载
历年真题
历年考试真题试卷, 真实检验
章节练习
按章节做题, 系统练习不遗漏
考前押题
考前押题, 提高分数
模拟试题
海量考试试卷及答案, 分数评估
进入题库
相关试卷
综合练习
章节练习
组织影响与项目生命周期
项目整合管理(四)
项目整体管理
项目质量管理
项目质量管理(一)
项目质量管理(二)
项目质量管理(三)
项目质量管理(四)
项目质量管理(五)
引论
收藏本站
Ctrl+D
将本站加入到书签,做题找题搜题,快速快捷。
下载App
微信扫一扫打开
回到顶部