Which of the following statements is true about the WBS?

  • A.The WBS is a deliverable oriented hierarchical decomposition of the work to be executed by the project team, to accomplish the project objectives and create the required deliverable
  • B.The WBS is an unstructured list of activities in chart for
  • C.The WBS is the same as the organizational breakdown structur
  • D.The WBS refers to the bill of material