Two months into a design project, the customer requested a modification to the project. The change w...
Two months into a design project, the customer requested a modification to the project. The change was made a without notify the project manager. During the final testing phase, result were different from what was planned for, This scenario is an example of which of following?
参考答案: C
参考解析: 如果当时恰当地记录了范围变更,完全可能立刻提出该项变更的影响。这道题考的是使用范围变更控制的重要性。
在一个设计项目开始两个月后,客户要求对产品作修改。在没有通知项目经理的前提下就做了这项变更。在最终测试阶段,测试结果与当初计划的不同。这种情况是下列哪项的例子?
A) 测试计划定义不完善。
B) 质量管理计划的开发不完善。
C) 使用范围变更控制的技能差。
D) 不坚持沟通计划。