单选题 1分

You are working on a telecommunication project. The product and system requirements have been determ...

You are working on a telecommunication project. The product and system requirements have been determined and agreed to by the customer, your management, and other key stakeholders. Work is proceeding on the project according to schedule. Everyone seems pleased with the progress to date. You have just learned that a new regulatory requirement will cause a change in one of the project's performance specification. To ensure that this change is incorporated onto the project plan, you should ______.
  • A.call a meeting of the change control board
  • B.change the WBS, project schedule, and project plan to reflect the new requirement
  • C.prepare a change request
  • D.immediately inform all affected stakeholders of the new approach to take on tee project

你可能感兴趣的试题

1 单选题 1分
  • A.Check the work completed against the correct scope statements.
  • B.Review the scope of work with the stakeholders.
  • C.Document the inconsistencies to management, calculating the cost of nonconformanc
  • D.Stop all activities until the scope of the work complet
2 单选题 1分
  • A.record all the changes
  • B.provide documentation on all the changes to the sponsor
  • C.make sure the changes are reflected in the project scope
  • D.prevent more changes from occurring
4 单选题 1分
  • A.Tell the team member to take a corrective action.
  • B.Determine if the alternative way is acceptable to the functional manager.
  • C.Ask the team member if the changes are necessary.
  • D.Determine if the changes also change the scope of the work packag