单选题
1分
You are working on a telecommunication project. The product and system requirements have been determ...
You are working on a telecommunication project. The product and system requirements have been determined and agreed to by the customer, your management, and other key stakeholders. Work is proceeding on the project according to schedule. Everyone seems pleased with the progress to date. You have just learned that a new regulatory requirement will cause a change in one of the project's performance specification. To ensure that this change is incorporated onto the project plan, you should ______.
参考答案: C
参考解析: 在做A和B之前,首先应该做C。而D应该是在该变更通过变更管理过程而被接受以后。
你正在管理通信项目。客户,你的上级和其他有关方面都已经确定和批准了产品和系统要求。项目按照时间表实施。到目前为止似乎每个人对进度感到满意。你刚刚得知一个新的管理规定将引起一个项目执行标准发生变更。为保证该变更包括在项目计划中,你应该______。
A) 召开变更控制委员会会议
B) 修改WBS、项目时间表和项目计划,以反映新的规定和要求
C) 准备变更请求
D) 立即通知受到影响的各位干系人有关项目实施的变更内容